Here Are This Week’s Road Construction Problem Spots
July 8, 2019
Drivers will encounter traffic disruptions on the following state roads and projects in Escambia and Santa Rosa counties as crews perform construction and maintenance activities.
Escambia County:
- U.S. 29 Widening from Interstate 10 (I-10) to U.S. 90A (Nine Mile Road) – Nine Mile Road will be closed at the U.S. 29 from 8 p.m. to 6 a.m. Monday, July 8 through Thursday, July 11 and from 8 p.m. to 6 a.m. Sunday, July 14 through Thursday, July 18 as crews drive piles for the new southbound bridge deck. Traffic control officers will be on-site to help direct motorists. The following detour will be in place:
- Eastbound Nine Mile Road will be reduced to one lane, directed to U.S. 29 southbound, U-turn at West Hood Drive, and return to Nine Mile Road.
- Westbound traffic will perform the same operation at West 9 1/2 Mile Road.
U.S. 29 traffic between Interstate 10 and 9 1/2 Mile Road may experience alternating lane closures as crews continue drainage and paving operations.
- Nine Mile Road (S.R. 10/U.S. 90A) Widening from Pine Forest Road to U.S. 29 – Cove Avenue north of 9 Mile Road will be closed from 7 a.m. Tuesday, July 9 to 5 p.m. Saturday, July 13 to perform drainage improvements. Traffic will be detoured to West 9 and a Half Mile Road and Fowler Avenue. Detour signs and variable message boards are in place to alert drivers of the temporary road closure and detour routes.
- U.S. 98 Pensacola Bay Bridge Replacement Bridge- Bridge construction will require the following lane closures from 8 p.m. to 5 a.m. Sunday, July 9 through Sunday, July 16:
-
- Intermittent east and westbound lane closures on U.S. 98 from North 14th Avenue in Pensacola to east of the Pensacola Bay Bridge in Gulf Breeze.
- Intermittent lane closures on North 17th Avenue in Pensacola between U.S. 98 and the CSX Railroad overpass (Graffiti Bridge).
- S.R. 291 (Davis Highway) at Brent Lane Turn Lane Construction- Motorists will encounter southbound, outside lane restrictions on Davis highway at Brent Lane from 8 p.m. Monday, July 8 to 5 a.m. Tuesday, July 9 as crews construct a right turn only entrance.
- I-10 over Perdido River Pavement Testing- There will be alternating east and westbound, outside lane closures on I-10 over the Perdido River at the Florida-Alabama line from 8 p.m. to 5 a.m. Tuesday, July 9 and Wednesday, July 10 as crews perform pavement testing operations.
- I-10 over the Choctaw River Relief Routine Bride Inspection- Drivers will encounter alternating east and westbound lane restrictions on I-10 over the east and west Choctaw River Relief Bridges from 9 a.m. to 3 p.m. Tuesday, July 9 as crews perform a routine bridge inspection.
- State Road (S.R.) 727 (Fairfield Drive) from South of Usher Circle to North of Hestia Place- Traffic on Fairfield Drive from south of Usher Circle to north of Hestia Place was shifted from its current alignment to the west Tuesday, June 18 to allow crews to complete the installation of the box culvert under the roadway. The north entrance to Usher Circle will also be temporarily closed to traffic during the drainage operation. Residents will utilize the south entrance of Usher Circle. The temporary lane shift and road closure is anticipated to take place for approximately three weeks.
- County Road (C.R.) 168 Bridge Replacement over Unnamed Branch in Northwest Century- Traffic was shifted onto a temporary bridge Wednesday, July 3 and the existing roadway will be closed to traffic and the temporary diversion will remain in place throughout the construction of the new bridge. Activities associated with the bridge replacement project continue and are anticipated to be complete late 2019.
- Crary Road Bridge Replacement over Pritchett Mill Creek- Crary Road is closed between Tedder Road and Byrneville Road as crews continue to construct a bridge culvert. Motorists will be detoured via C.R. 4 and Byrneville Road. The project is anticipated to be complete summer 2019.
- Bratt Road Bridge Replacement over Canoe Creek - Bratt Road will continue to be closed near Canoe Creek. Drivers on Bratt Road, west of the bridge, will be detoured to Pine Barren Road and C.R. 4. Drivers east of the bridge will be detoured east on Bratt Road. The project is anticipated to be complete summer 2019.
- Hanks Road Bridge Replacement over Breastworks Creek - Construction activities continue. The roadway will be temporarily closed during construction. Drivers on Hanks Road, west of the bridge, will be detoured to C.R. 99 and C.R. 4. Drivers east of the bridge will utilize Pine Barren Road.
Santa Rosa County:
- U.S. 98 Pensacola Bay Bridge Replacement Bridge- Bridge construction will require the following lane closures from 8 p.m. to 5 a.m. Sunday, July 9 through Sunday, July 16:
- Intermittent east and westbound lane closures on U.S. 98 from North 14th Avenue in Pensacola to east of the Pensacola Bay Bridge in Gulf Breeze.
- Intermittent lane closures on North 17th Avenue in Pensacola between U.S. 98 and the CSX Railroad overpass (Graffiti Bridge).
- I-10 Widening from the Escambia Bay Bridge to Avalon Boulevard (S.R. 281/Exit 22) – The following construction related traffic impacts are planned for Interstate 10 and Avalon Boulevard from 8 p.m. to 6 a.m. the week of Monday, July 8:
o Alternating lane closures, Tuesday through Thursday, on Avalon Boulevard near the I-10 interchange as crews perform construction activities.
o Alternating lane closures on I-10 from the Escambia Bay Bridge to east of Avalon Boulevard (Exit 22), Tuesday through Thursday, as crews work to place final striping and to finish work list items.
- S.R. 87 Pavement Markings Replacement- Traffic will encounter alternating and intermittent minor delays at the following locations from 8 p.m. to 5 a.m. Sunday through Friday until Thursday, July 30 as crews remove and replace pavement markings in the roadway. Law enforcement will be on site to direct traffic:
-
- U.S. 90 to Nicholas Lake Road
- U.S. 98 to Vonnie Tolbert Road
- S.R. 87 Multilane from Eglin AFB boundary to Hickory Hammock Road– All north and southbound travel lanes on State Road (S.R.) 87, between County Road (C.R.) 184 (Hickory Hammock Road) and two miles south of the Yellow River are now open and the speed limit is now 65 mph. Drivers will encounter intermittent lane closures as crews complete construction activities and the speed limit is reduced to 45 mph through the active work zones.
All activities are weather dependent and may be delayed or rescheduled in the event of inclement weather. Drivers are reminded to use caution, especially at night, when traveling through a work zone and to watch for construction workers and equipment entering and exiting the roadway.