FDOT: Weekly Traffic Alerts

October 11, 2016

Drivers will encounter traffic disruptions on the following state roads in Escambia and Santa Rosa counties as crews perform construction and maintenance activities this week.

Escambia County:

  • 9 Mile Road (S.R. 10/U.S. 90A) from Beulah Road to Pine Forest Road - Clearing of trees and shrubs on the 4.8-mile segment has begun. Lane closures are only permitted between the hours of 8 p.m. and 6 a.m.
  • U.S. 29 (S.R. 95) Widening from I-10 to 9 Mile Road – Crews have begun clearing operations for pond locations.  Motorists will see activity in relation to this near the intersection of Ryan Avenue and Detroit Boulevard. Lane closures will only be permitted between 8 p.m. and 6 a.m.
  • State Road 292 (Perdido Key Drive) Resurfacing (from Alabama State Line to ICWW Bridge) – Intermittent and alternating daytime lane closures for approximately two weeks as crews mill  and place the structural course of asphalt.
  • State Road (S.R) 298/Lillian Highway Maintenance Operations- Lane closure between Fairfield Drive and Blue Angel Highway Wednesday, Oct. 12 from 10 a.m. to noon as crews perform routine maintenance on a box culvert.
  • Cervantes Street (U.S. 90) Underground Utility Work- Eastbound lane closure from 8 p.m. Thursday, Oct. 13 to 6 a.m. Friday, Oct. 14 as crews perform underground utility work.

Santa Rosa County:

  • Interstate 10 (I-10) Widening from Escambia Bay Bridge to Avalon Boulevard- Alternating lane closures, between the Escambia Bay Bridge and S.R. 281 (Avalon Boulevard/Exit 22), from 8 p.m. to 6 a.m. Monday, Oct. 10 through Thursday, Oct. 13 as crews continue widening work. In addition, there will be alternating lane closures on Avalon Boulevard near the I-10 interchange for bridge work.
  • I-10 Resurfacing from east of S.R. 87 to the Okaloosa County Line – Intermittent and alternating lane closures east and westbound between the S.R. 87 interchange and the Okaloosa County line from 8 p.m. to 6 a.m. Monday, Oct. 10 through Friday, Oct. 14 as crews perform construction activities.  Motorists are reminded the speed limit is reduced to 60 MPH within the lane closure.
  • S.R. 87 Widening from two miles south of the Yellow River to Hickory Hammock Road –The Yellow River beneath the S.R. 87 bridge will be temporarily closed Friday, Oct. 14 from 7 a.m. to 6 p.m. as crews mobilize equipment for construction of the new northbound bridge.  Boaters are advised to avoid this area.

All activities are weather dependent and may be delayed or rescheduled in the event of inclement weather. Drivers are reminded to use caution, especially at night, when traveling in a work zone and to watch for construction workers and equipment entering and exiting the roadway.