Almost $21 million in North Escambia road and bridge projects are included in Florida’s 2016-2017 budget that was recently signed by Gov. Rick Scott.

Projects in the North Escambia area that received funding were:

BRIDGE REPLACEMENTS

  • Molino Road over Pensaula Creek Bridge $1,157,752
    • The bridge was constructed in 1958 and is located west of Highway 29 between 4 Star Farm Road and Sunshine Hill Road.
  • Highway 97A over Boggy Creek Bridge $2,967,954
    • The bridge was constructed in 1969 and is located on Highway 97A about one mile west of the Highway 97A and Highway 99 intersection near Enon.
  • Highway 99 over Pine Barren Creek $3,815,089
    • The bridge was constructed in 1955 and is located on North Highway 99 north of Gobbler Road, near the Oak Grove Park.
  • Highway 99A over Boggy Creek $1,741 ,636
    • The bridge was constructed in 1968 and is located on Highway 99A (Arthur Brown Road) just west of Walnut Hill Baptist Church.

WIDENING AND DRAINAGE

  • Muscogee Road Widening and Drainage Improvements $1,674,000

PRELIMINARY ENGINEERING

  • 9 Mile Road from Highway 90 to Beulah Road $1,000,000
  • Highway 29 from south of Muscogee Road to Highway 97 (resurfacing) $1,200,000

RESURFACING

  • Highway 4 from Highway 29 to Escambia River Bridge  $1,058,585
  • Highway 29 from north of Highway 90 to south of Muscogee Road  $6,306,108

Pictured top: The Molino Road bridge over Penasula Creek. Pictured: The deteriorating wood pilings that support the bridge. NorthEscambia.com photos, click to enlarge.

Comments

11 Responses to “State Budget Includes $21 Million For North Escambia Road, Bridge Projects”

  1. 429SCJ on April 15th, 2016 10:35 am

    There is a killer pot hole on the 164 west, just as you approach the 164/99A crossroads., heading east. I had to hit it a few times to get a dose of negative reinforcement, for to avoid it.

    Commissioners! If you keep the roads and their ancillaries in good working order, then 90% plus of your keeping your constituents happy requirements are satisfied.

  2. chris in Molino on April 14th, 2016 5:57 am

    Liz, I know you and Ricky need a pave on your road but I for one can’t wait until the little bridge is started. They say Molino Rd. will be shut down for six months. So i’ll be able to pull out of the driveway, check mail, and take garbage out without fear of an 80 mph driver (which is frequent). People walk, kids ride bikes, ride horses, even drive horse buggies along the road yet fools act like it’s their racetrack. I may even put up a sign at Sunshine Hill with a smiley face saying, “Ha Ha, Go Around” !

  3. mick on April 14th, 2016 2:03 am

    With double row reflectors on 99, although visually helpful, they have made the lanes narrower, not to mention unfinished shoulder work – and while were are at it – the completed bridge on 97 has an unacceptable bumps going both north and south – this needs to be fixed

  4. Willis on April 13th, 2016 9:06 pm

    @cw
    What you may not know about their “cheap patch job on hwy 99 ” is the road was supposed to be resurfaced shortly after that work was completed. Ball dropped.

    I for one say it is much better than it was. I don’t remember any bus mirrors knocked off or busted tire issues from dropping off the edge(wrecks) since they did this work.

    But Yes 99 north needs resurfacing.

  5. CW on April 13th, 2016 2:02 pm

    John,
    If that were to happen it would be one extremely poor county, and there wouldn’t be much money to go around for anything. I’m sure the north end benefits from the property taxes paid by the south end, whether it seems like it or not.

  6. john otnes on April 13th, 2016 1:18 pm

    WELL I STILL SAY IT’S TIME WE HAVE A COUNTY FOR US ,NOT THE SOUTH END. LIKE NORTH ESCAMBIA COUNTY. THEN WE COULD GET SOMETIME DONE AND WE WOULD NOT HAVE TO LOOK TO THE SOUTH END FOR HELP.. YES NORTH ESCAMBIA COUNTY LOOK TO ME TO HACE OR OWN COUNTY !!!!!!!!!

  7. liz fillingim on April 13th, 2016 12:48 pm

    SOO,close to FOUR STAR FARM ROAD, but the County allways Overlooks us on this road . It has been raining alot lately, which means our ROAD is EXTREMLY MUDDY and makes the POTHOLES which are large and so close together it feels like its going to warp the Undercarage of our Vehicles.The little Bridge they are talikng about is in GOOD SHAPE,it has never flooded or caused anyone a problem. Please COUNTY get your head out of the CLOUDS and do your job for us Taxpayers.

  8. billy jim on April 13th, 2016 12:25 pm

    WHAT ABOUT PINE BARREN RD BETWEEN HANKS RD. AND BREASTWORK

  9. FLA girl on April 13th, 2016 7:53 am

    Oh my goodness…repave and widen Hwy 4 from Hwy 29 to Hwy 97!!! Horrible road!!!

  10. CW on April 13th, 2016 5:26 am

    @Justsaying

    I agree with you, hwy99 to the state line is terrible. The way they did a cheap patch job to the edges to widen it years ago made it awful, you nearly need to ride in the center of the road to get a smooth ride.

  11. Justsaying on April 13th, 2016 4:25 am

    Lot of good projects. Highway 99 between 97 and the Alabama line is still not in any plans. Maybe after the bridge job. We can only hope.