Century Street Paving Project Underway
June 2, 2015
Work should be complete in the next two weeks, weather permitting, to resurface and patch a dozen streets around Century.
The total cost will be $153,122.69 to contractor Roads, Inc. The project was not be bid; the council piggybacked on an existing Escambia County contract with Roads.
The following streets will be resurfaced or patched as noted:
- Jefferson Avenue – Resurface from curve at Mincey Lane to railroad tracks – $11,467.50
- Jefferson Avenue – Patch near Carver Community Center – $696
- Robert Road — Patch – $319
- Tedder Road – Patch near fire station $1,517
- Pond Street – Resurface from Century Business Center to bridge near sewer plant – $32,817.90
- Pinewood Avenue – Resurface from Hecker to Front Street – $17,701.65
- Mayo Street – Resurface from Hecker to Front Street – $25,437
- Mayo Lane – Resurface from Mayor Street to Jefferson Avenue – $16,367
- Kelly Field Road – Pave gravel road beside railroad tracks – $6,090
- Kelly Field R0ad – Overlay section between ball field and cemetery – $6,595.65
- Kelly Field Road – Resurface from Hecker Road to ballpark gate - $8,201
- Lodge Drive – Resurface from Hecker to Front Street $12,690.70
- Wood Street – Resurface from Lodge Drive to Bradley – $4,746.85
- Hecker Road -Parch near Alger Road – $725
- Renfroe Street – Resurface from Hwy 29 to Ivey Street – $5,650.35
The contract also includes mobilization fee of $2,100.