Bids Awarded For Ransom Renovations, Jim Allen Windows

March 3, 2013

The Escambia County School Board has awarded a bid to Vision Construction, Inc. for general renovations at Ransom Middle School and for window replacements at Jim Allen Elementary School.

The general renovations at Ransom Middle School will cost $68,800 of the total $126,400 bid. The window replacements at Jim Allen Elementary School will cost $49,700 plus an alternative amount of $7,900 for bathroom windows. The project is funded by half cent sales tax monies.

There were a total of seven bids received on the projects, ranging from the low bid of $126,400 by Vision Construction to $235,000 by The Green-Simmons Company. Second lowest bid was $132,800 by Southeastern Construction, Inc.