Bratt Elementary Renovations Final Total: Just Under One Million

November 18, 2009

bratt10.jpg

The final bill is in for building renovations at Bratt Elementary School – $975,660.35. The Escambia County School approved paying the bill at their Tuesday night meeting.

The renovations took place in the front/west wing of the school and  included new windows, doors, and floors for the building that was constructed in 1980. It also included the installation of a central heating and cooling system. The main portion of the renovation contract was $770,500.

The board approved additional renovations at the school when the original contract was awarded, including:

  • replace restroom fixtures in the west wing, $3,425
  • replace lighting and ceilings in west wing, $36,500
  • renovations in guidance and administration areas, $26,000
  • replace air handling units in cafetorium, $82,600
  • replace water meter and piping for increased water pressure, $27,382

The total contract awarded last March was $946,407 to Morette Company of Pensacola. There were a total of nine bidders on the project, with five bids coming in at over $1 million.

During the project, there were several deletions and additions to the contract, including:

  • replace restroom fixtures in the west wing, $3,425
  • replace lighting and ceilings in west wing, $36,500
  • renovations in guidance and administration areas, $26,000
  • replace air handling units in cafetorium, $82,600
  • replace water meter and piping for increased water pressure, $27,382
  • replace existing electrical outlet covers with stainless steel covers, $727.67 (principal’s request)
  • move electrical disconnect in stage area and existing conduit in room 25, $702.03 (contractor’s request)
  • paint bathroom ceilings to match wall color and paint existing doors and frames, $754.36 (principal’s request)
  • modify transaction counter at front office by raising it approximately six inches, $678.76 (principal’s request)
  • add electrical ground bus bar for additional surge protection for communications system, $698.14 (engineer’s request)
  • modify existing boiler, $713.41 (owner’s request)
  • lower urinal in bathroom (Room 16), $949.78 (principal’s request)

The project was funded from capital construction monies from the half cent sales tax.

NorthEscambia.com file photo, click to enlarge.

Comments

2 Responses to “Bratt Elementary Renovations Final Total: Just Under One Million”

  1. robert on November 18th, 2009 9:37 am

    I don’t think anyone liked the idea of closing that school and bringing the kids to Bratt. I think they are just trying to get the schools closer together to help with maintenance problems.

  2. Century girl on November 18th, 2009 12:29 am

    Wow! Closing Carver-Century sure saved a lot of money…LOL
    perhaps it would have saved lots of $$ to bus the Bratt children to the already recently renovated Carver-Century building since Bratt required such extensive renovation. Looks like the project ran slightly over budget..nearly doubled if I remember correctly.