Current Survey Work Leading To Highway 97 Being Resurfaced

December 5, 2007

hwy97survey.jpg

Survey work currently underway along Highway 97 in North Escambia is in preparation for the resurfacing of the road beginning in late 2009.

The $1.77 million survey and design phase of the project is ongoing, said Tommie Speights, Public Information Director for District 3 of the Florida Department of Transportation. The survey work and preliminary engineering is being conducted by Volkert and Associates of Mobile. The survey is expected to be finished by January of next year.

“The project is scheduled to let for contract in August 2009,” Speights told NorthEscambia.com. “It would then take three to four months to begin actual resurfacing, so work would begin in about December of 2009.”

Budget figures show that the resurfacing project is expected to cost $17.1 million and be completed in 2010. The entire roadway is be repaved from Country Road 95 (Old Palafox) across Highway 29 to the Alabama state line, a distance of about 23 miles. No major drainage changes are expected to the route’s 55 cross drains under the highway, with the exception of some possible changes near the intersection of Highway 97 and Crabtree Church Road.

Existing 12 foot wide travel lanes and five foot paved shoulders will be milled and resurfaced. This project does not include the four-laning of Highway 97. A four lane highway is not in any of the state’s current plans for Highway 97.